Quanzhou section of Union Road in Quanxia Zhangcheng is fully connected泉厦漳城市联盟路泉州段全线贯通

Column:Industry Information Time:2020-03-27


  At 4:00 a.m. on March 26, the control project of Quanxia-Zhang City Alliance Road, the right steel box girder of Anhaiwan Sea-crossing Bridge, was hoisted, and the closure was successfully completed, marking the completion of the 27.3-kilometer Quanzhou section of Quanzhou-Xiamen City Alliance Road.
     3月26日凌晨4点,泉厦漳城市联盟路控制性工程——安海湾跨海大桥右幅钢箱梁吊装完成,顺利实现合龙,标志着泉厦漳城市联盟路泉州段27.3公里全线贯通。

  The main bridge of the Anhaiwan Sea-Crossing Bridge is designed as a continuous rigid frame bridge with mixed beams, with a total length of 570 meters and a combined span of (135+300+135) meters. In order to ensure the successful completion of the hoisting operation, the provincial high-level index and the provincial traffic quality and safety center organized professional and technical personnel to go deep into the hoisting construction front line, adopted information technology to check the hoisting plan in advance and the on-site "point-to-point" supervision mode, and did a good job of on-site service. Good quality and safety of the main bridge hoisting Helong.
    安海湾跨海大桥主桥设计为混合梁连续刚构桥,全长570米,跨径组合(135+300+135)米,为目前国内同类型桥梁中第二大跨径,在建第一大跨径。为确保此次吊装作业顺利完成,省高指、省交通质安中心组织专业技术人员深入吊装施工一线,采取信息化手段提前查阅吊装方案和现场“点对点”督查模式,做好现场服务,把好主桥吊装合龙质量安全关。


  The Quanzhou section of Union Road in Quanzhou, Xiamen, and Zhangzhou is expected to open to traffic in the first half of this year, which will further shorten the distance from Quanzhou Taiwanese Investment Zone, Shishi, southern Jinjiang, southern Nan'an and other areas to central cities such as Xiamen and Zhangzhou. It is of great significance to facilitate the travel of the masses and promote the economic development along the route. (Provincial Transportation Quality and Safety Center, Provincial High Index, CCCC Quanzhou Expressway Company)
    泉厦漳城市联盟路泉州段预计今年上半年实现通车,将进一步缩短泉州台商投资区、石狮、晋江南部、南安南部等地区通往厦门、漳州等中心城市的距离,对织密高速公路网络、方便群众出行、推动沿线经济发展具有重要意义。(省交通质安中心、省高指、中交泉州高速公司)